Do not change any of the risk management template formulae.
Question 1
Identity your project’s risks
Using the RMP template and after discussion with your supervisor, complete the left hand side of Part 2: Risk Register (i.e. the first five columns, ending in “Risk Consequencesâ€. You should list at least 8 possible risks.
Details of fields in the RMP Risk Register:
- Risk Ref. No: This is just a sequential number, used as a key for associating with the Risk Treatment Plan.
- Category: Select Commercial, Finance, Security, Safety, or Legal/Regulatory from the drop down list. You may have more than one risk in a category.
- Risk Description: e.g. “Older scanners may not work under Windows 12â€.
- Risk Cause: e.g. “Drivers may not exist for Windows 12â€.
- Risk Consequences: e.g. “Invoices cannot be scanned inâ€.
Upload your updated template to the Forum by Wednesday night.
Question 2
Analyse your project’s risks
Analyse the risks in your project; you may discuss these with your supervisor. Using the RMP template again, complete the right hand side of Part 2: Risk Register (i.e. Impact and Likelihood). Do not change the Rating column, it will be calculated for you automatically by the spreadsheet.
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.